MSUnet Backbone Upgrade - TB13010

This item provides information on these topics:

Overview

Academic Technology Services (ATS) is upgrading the MSUnet campus network backbone since the existing network backbone is reaching capacity. This project will upgrade the core routing from the current 1Gigabit (Gb) building routers to two carrier-class 10Gb routers and will bring 10Gb networking directly to 80 buildings. The project is expected to be fully complete within the next year. The ability to add remaining campus buildings will be available upon completion.

Once completed, the upgraded and more centralized campus network backbone will allow for expected growth in network traffic across campus and to the Internet, as well as making the backbone less vulnerable to power outages. It will also help ATS offer new services to the MSU community, such as campus-wide departmental VLANs and centralized departmental firewall and IPS protection.

The initial design, specification, and testing have been completed with central routing and security installations expected to be completed by January 2010. Individual buildings will start migrating to the new 10Gb network backbone as early as October 2009, with all 80 buildings scheduled to be converted by summer 2010.

As various phases of the project are completed, a number of network service interruptions will need to be scheduled between 5:00am and 7:00am. ATS will always strive to minimize the duration and impact of any service interruption. For a detailed list of services affected and corresponding dates, read Which MSU computing and networking services may be affected and when?

Why is an upgrade to the campus backbone needed?

The MSUnet backbone is currently composed of ninety 1Gb building routers which are nearing maximum capacity. The new equipment will be composed of two 10Gb router systems located in different buildings for increased bandwidth, security, and redundancy. The upgraded system will include more than one hundred 10Gb switching systems in 80 buildings. This upgrade is required to minimize overload conditions and provide for a more robust campus network with the ability to accommodate future growth.

Which MSU computing and networking services will be affected and when?

As various phases of the project are completed, a number of network service interruptions will need to be scheduled between 5:00am and 7:00am. The schedules below are subject to change, but will be updated as information becomes available.


Phase 1 – Connecting SRX5800 as Border Security Device - COMPLETED

Phase 1 of the 10Gb network upgrade project, which involved connecting SRX5800 for network border security, has been completed. All border IPS functions were migrated to the SRX5800 during August 2009.


Phase 2 – Cutover of MX960/SRX5800 in Communication Arts
- COMPLETED

MX960/SRX5800 equipment will be installed in the Communications Arts building, and traffic will be redirected through them as they become the primary router and security enforcement for the MSU network. It will also provide redundancy to the system. After the Communications Arts MX960/SRX5800 has been stable for about a week, the 1Gb IPSs will be removed from the Computer Center.


Phase 3 – Cutover of Second MX960/SRX5800 Pair in the Computer Center
- COMPLETED

The second pair of MX960/SRX5800 will be installed in the Computer Center providing full redundancy of core routing and security enforcement. The existing 10Gb border firewalls will be removed.


Phase 4a – Moving Wells Hall and Anthony Hall to the 10Gbps Backbone
These two buildings will allow for early evaluation of the cutover process.

Building

Tier-2 Installed in Existing Network as Building VSW

Tier-2 Cutover to 10Gb Backbone

Wells

Completed

Completed

Anthony

Completed

Completed


Phase 4b – Moving 19 Buildings to the 10Gb Backbone during Winter Break 2009


Building

Tier-2 Installed in Existing Network as Building VSW

Tier-2 Cutover to 10G Backbone

Farrall

Completed

Wednesday, December 30, 2009

Biochemistry

Completed

Wednesday, December 30, 2009

Biomedical and Physical Sciences (BPS)

Completed

Wednesday, December 30, 2009

Chemistry

Completed

Wednesday, December 30, 2009

Computer Center

Completed

Monday, December 28, 2009

Tuesday, December 29, 2009

Administration Building

Completed

Monday, December 28, 2009

Tuesday, December 29, 2009

Engineering

Completed

Monday, December 28, 2009

Communication Arts

Completed

Monday, December 28, 2009

Plant and Soil Science

Completed

Monday, January 04, 2010

Vet Clinic

Completed

Monday, January 04, 2010

Life Science

Completed

Monday, January 04, 2010

Engineering Research

Tuesday, November 17, 2009

Monday, January 04, 2010

Clinical Center

Thursday, November 19, 2009

Tuesday, January 05, 2010

Radiology

Tuesday, November 24, 2009

Tuesday, January 05, 2010

Fee Hall

Tuesday, December 01, 2009

Tuesday, January 05, 2010

Wharton Center

Thursday, December 03, 2009

Tuesday, January 05, 2010

Snyder Hall

Tuesday, December 08, 2009

Wednesday, January 06, 2010

Business College Complex

Thursday, December 10, 2009

Wednesday, January 06, 2010

Law

Tuesday, December 15, 2009

Wednesday, January 06, 2010


Phase 4c – Moving 21 Buildings to the 10Gb Backbone during First Quarter 2010


Building

Tier-2 Installed in Existing Network as Building VSW

Tier-2 Cutover to 10G Backbone

Manly Miles

Tuesday, January 12, 2010

Friday, January 29, 2010

University Housing

Thursday, January 14, 2010

Friday, January 29, 2010

University Services

Tuesday, January 19, 2010

Friday, January 29, 2010

Food Stores

Thursday, January 21, 2010

Friday, January 29, 2010

Power Plant

Tuesday, January 26, 2010

Friday, January 29, 2010

Kedzie Hall

Thursday, January 28, 2010

Friday, February 12, 2010

Psychology

Tuesday, February 02, 2010

Friday, February 12, 2010

Cyclotron

Yet To Be Determined

Yet To Be Determined

Food Science

Yet To Be Determined

Yet To Be Determined

McDonel Hall

Thursday, February 11, 2010

Friday, February 26, 2010

Holmes Hall

Tuesday, February 16, 2010

Friday, February 26, 2010

Akers Hall

Thursday, February 18, 2010

Friday, February 26, 2010

Hubbard Hall

Tuesday, February 23, 2010

Friday, February 26, 2010

Natural Resources

Thursday, February 25, 2010

Friday, March 05, 2010

Plant Biology

Tuesday, March 02, 2010

Friday, March 05, 2010

Food Safety

Thursday, March 04, 2010

Friday, March 05, 2010

Brody Hall

Tuesday, March 09, 2010

Friday, March 26, 2010

Kellogg Center

Thursday, March 11, 2010

Friday, March 26, 2010

Jenison

Tuesday, March 16, 2010

Friday, March 26, 2010

Spartan Stadium

Thursday, March 18, 2010

Friday, March 26, 2010

Clara Bell Smith Center

Tuesday, March 23, 2010

Friday, March 26, 2010


Phase 4d – Moving 26 Buildings to the 10Gb Backbone during the Second Quarter 2010


Building

Tier-2 Installed in Existing Network as Building VSW

Tier-2 Cutover to 10G Backbone

Campbell Hall

Thursday, March 25, 2010

Friday, April 09, 2010

Union

Tuesday, March 30, 2010

Friday, April 09, 2010

Human Ecology

Thursday, April 01, 2010

Friday, April 09, 2010

Owen Hall

Tuesday, April 06, 2010

Friday, April 09, 2010

Linton

Thursday, April 08, 2010

Friday, April 23, 2010

Ag Hall

Tuesday, April 13, 2010

Friday, April 23, 2010

Natural Science

Thursday, April 15, 2010

Friday, April 23, 2010

Giltner

Tuesday, April 20, 2010

Friday, April 23, 2010

Auditorium

Thursday, April 22, 2010

Friday, April 23, 2010

Bessey

Tuesday, April 27, 2010

Friday, May 07, 2010

Shaw

Thursday, April 29, 2010

Friday, May 07, 2010

Erickson

Tuesday, May 04, 2010

Friday, May 07, 2010

International Center

Thursday, May 06, 2010

Friday, May 07, 2010

Olin

Tuesday, May 11, 2010

Friday, May 28, 2010

Old Horticulture

Thursday, May 13, 2010

Friday, May 28, 2010

Berkey

Tuesday, May 18, 2010

Friday, May 28, 2010

Student Services

Thursday, May 20, 2010

Friday, May 28, 2010

Mason/Abbott

Tuesday, May 25, 2010

Friday, May 28, 2010

Wonders Hall

Thursday, May 27, 2010

Friday, June 11, 2010

Wilson Hall

Tuesday, June 01, 2010

Friday, June 11, 2010

Holden Hall

Thursday, June 03, 2010

Friday, June 11, 2010

University Printing

Tuesday, June 08, 2010

Friday, June 11, 2010

Nisbet

Thursday, June 10, 2010

Friday, June 11, 2010

Breslin
Tuesday, June 15, 2010
Friday, June 25, 2010

Case Hall

Tuesday, June 15, 2010

Friday, June 25, 2010

Physical Plant

Thursday, June 17, 2010

Friday, June 25, 2010

Public Safety

Tuesday, June 22, 2010

Friday, June 25, 2010


Phase 4e – Moving 8 Buildings to the 10Gb Backbone during the Third Quarter 2010

Building

Tier-2 Installed in Existing Network as Building VSW

Tier-2 Cutover to 10G Backbone

MSU Museum

Thursday, June 24, 2010

Friday, July 09, 2010

Olds Hall

Tuesday, June 29, 2010

Friday, July 09, 2010

Main Library

Thursday, July 01, 2010

Friday, July 09, 2010

Urban Planning and Landscape Architecture (UPLA)

Tuesday, July 06, 2010

Friday, July 09, 2010

James B. Henry Center for Executive Development

Tuesday, July 13, 2010

Friday, July 23, 2010

South Campus Communications Storage Building (SCCSB)

Thursday, July 15, 2010

Friday, July 23, 2010

Diagnostic Center for Population and Animal Health (DCPAH)

Tuesday, July 20, 2010

Friday, July 23, 2010

MSU Surplus and Recycling Center

Completed

Friday, July 23, 2010

Will status information be available during the upgrade?

This article will be kept up-to-date throughout the MSUnet backbone upgrade project. There will be some scheduled maintenance during each phase of the network upgrade project in preparation of building cutovers. Status updates regarding scheduled service interruptions will be posted at http://servicestatus.msu.edu.

If unforeseen problems occur and http://servicestatus.msu.edu is not available, an updated status message will be available when calling (517) 432-6200.

Might scheduled service interruptions take longer than expected?

It is possible more time will be needed. Status updates regarding scheduled service interruptions will be posted at http://servicestatus.msu.edu.

What if I still have questions?

Numerous efforts will be made throughout the duration of the MSUnet backbone upgrade to keep the MSU community informed of the progress. Discussion about the project will take place on the IT Exchange discussion board at http://forums.msu.edu, and updates will be provided in IT Exchange meetings.

If you are interested in finding out more about how the MSUnet Backbone Upgrade will affect your building or would like to schedule a department presentation, please contact the MSU ATS Help Desk at (517) 432-6200 or submit an electronic form at http://help.msu.edu.